Factors impacting construction project duration: A comparison between France, Germany and the UK
Proverbs, David; Holt, Gary D.; Olomolaiye, Paul
Authors
Gary D. Holt
Paul Olomolaiye Paul.Olomolaiye@uwe.ac.uk
Pro Vice-Chancellor Equalities and Civic Engagement
Abstract
A survey of contractors planning engineers in France, Germany the U.K. indicates significant differences between projected completion times for an identical model building. Completion times are shortest in France, followed by Germany and then the U.K. yielding means of 13, 18 and 22 weeks respectively. Investigations to elicit performance affecting resource utilisation factors provide some significant findings. The productivity rates for formwork operations, particularly those provided for floor slabs, correlated with completion times. This operation apparently provides the key to optimum completion times for high rise in situ construction. Analysis of variance provides evidence to indicate that preferred options for two particular construction methods can drastically impact upon completion times, these being preferred transportation and formwork (to columns) solutions. Shorter completion times were associated with tower crane\skip transportation solutions and, proprietary formwork. In terms of labour utilisation two factors demonstrated a significant relationship with project duration, namely numbers of supervisory personnel and allowance for daily relaxation\rest times. Shorter completion times were a feature of reduced supervisory numbers and longer periods of relaxation. Construction contractors may wish to give consideration to these important aspects, when planning to undertake such projects and earliest completion is paramount.
Journal Article Type | Article |
---|---|
Publication Date | Mar 1, 1998 |
Journal | Building and Environment |
Print ISSN | 0360-1323 |
Publisher | Elsevier |
Peer Reviewed | Peer Reviewed |
Volume | 34 |
Issue | 2 |
Pages | 197-204 |
DOI | https://doi.org/10.1016/S0360-1323%2898%2900004-3 |
Keywords | concrete construction, engineering, environmental, planning, contractors, productivity |
Public URL | https://uwe-repository.worktribe.com/output/1097088 |
Publisher URL | http://www.elsevier.com/ |
You might also like
Infrastructure procurement capacity gaps in Nigeria public sector institutions
(2019)
Journal Article
Development of sustainable assessment criteria for building materials selection
(-0001)
Journal Article
Construction stakeholder management
(2010)
Book
Downloadable Citations
About UWE Bristol Research Repository
Administrator e-mail: repository@uwe.ac.uk
This application uses the following open-source libraries:
SheetJS Community Edition
Apache License Version 2.0 (http://www.apache.org/licenses/)
PDF.js
Apache License Version 2.0 (http://www.apache.org/licenses/)
Font Awesome
SIL OFL 1.1 (http://scripts.sil.org/OFL)
MIT License (http://opensource.org/licenses/mit-license.html)
CC BY 3.0 ( http://creativecommons.org/licenses/by/3.0/)
Powered by Worktribe © 2025
Advanced Search